Construction Updates       

January 31, 2018 -

Drywall taping is underway in the basement. Mainfloor drywall has commenced. Mechanical and Electrical rough-ins continue. Suite showers have been set. Spray foam insulation has been completed. The flat roofs have been completed. HVAC installation has commenced. Sprinkler rough-ins continue throughout the building. How exciting to see drywall progress!

Exterior ProgressDrywall



January 17, 2018 - 

Thanks to the generosity of the Rotary Club of Vermilion members, we are building a spacious multi-purpose room with a Chapel. The views are stunning. The Rotary Room will be used for gatherings, events, community meetings and private functions. The room will seat 30, and tables and chairs have been ordered. There will be a small kitchen with sink and countertop. The Chapel will hold service on Sunday's. 

Rotary Multi-purpose Room View from Multi-purpose RoomAnother view from Multi-purpose room


January 2, 2018 -

The new building is coming together. All of the windows have been installed. Electrical work is going on throughout the building in the next few weeks. Water lines for the new showers are going in. Gyprock is being installed throughout. The washer, dryer and furnace have been moved into the building.            

Construction Progress


A stark contrast of old and new.

Old and New


November 19, 2017 -

The roof is getting put on the 1st wing of our modernization project! While that was being done, we held our Living Well Capital Campaign Kick-off Event, and got the first look at the interior! 

Roof going on!


Construction worker on roof


A first look

Entry way into the new Webb's Commercial Kitchen.

Dining Room/Elevators

Standing in what will be the new Dining Room. To the back will be where the elevators are located, and the back on the right is where the new Family Dining Room will be. 

Resident Room

A view into a new resident Room. 


October 16, 2017 - 

Wall partitions for the new suites and dining room are going up! 

Wall Partitions


September 28, 2017 - 

Framing is well underway!



August 26, 2017 - 

Basement walls are complete. Mechanical and electrical undergrounds are completed. Slab prep and poly are complete. Basement slabs are completed. Crawlspace backfill and radon rock are complete. Structural steel is complete. Damproofing, insulation, and weeping tile is complete. Backfill is complete. Wood framing material delivery has started. Basement pre-fabbed load bearing walls will start being installed, with main floor joists and basement wall loose framing to follow. 



August 10, 2017 - 
The concrete walls are finishing up. The elevator masonry is going up, and it will be over 10 m when it's done. Back fill is happening as walls have been poured. 
Mechanical is being done. The fire wall starts soon and will be 9 m. They are hoping for continued good weather and no wind.


June 23, 2017 -

According to Jen-Col superintendent, Kelly Roberts, construction progresses as planned.

On July 3, the foundations build will begin. It will take 4 to 6 weeks to have them finished.

Water and sewer will be installed as soon as the foundations are in.