Contruction Updates                     

October 16, 2017 - 

Wall partitions for the new suites and dining room are going up! 

Wall Partitions

 

September 28, 2017 - 

Framing is well underway!

Framing

 

August 26, 2017 - 

Basement walls are complete. Mechanical and electrical undergrounds are completed. Slab prep and poly are complete. Basement slabs are completed. Crawlspace backfill and radon rock are complete. Structural steel is complete. Damproofing, insulation, and weeping tile is complete. Backfill is complete. Wood framing material delivery has started. Basement pre-fabbed load bearing walls will start being installed, with main floor joists and basement wall loose framing to follow. 

 

 

August 10, 2017 - 
The concrete walls are finishing up. The elevator masonry is going up, and it will be over 10 m when it's done. Back fill is happening as walls have been poured. 
Mechanical is being done. The fire wall starts soon and will be 9 m. They are hoping for continued good weather and no wind.

 

June 23, 2017 -

According to Jen-Col superintendent, Kelly Roberts, construction progresses as planned.

On July 3, the foundations build will begin. It will take 4 to 6 weeks to have them finished.

Water and sewer will be installed as soon as the foundations are in.